| CONTRACT PRICE ADJUSTMENT SCHEDULE |
|
Back to Daily Tenders
1. Contract Price Adjustment Factor
In accordance with Clause 49(2), the value of each certificate issued in terms of Clause 52(1) shall be increased
in which the symbols have the following meanings:
Appendix thisproportion shall be 0,15. "a", "b", "c" and "d" are the co-efficients determined by the Engineer and specified in the Appendix, which are deemed,irrespective of the actual constituents of the work, to represent the proportionate value of labour, plant, materials (other than "special materials" specified, in terms of Clause 49(3), in the Appendix) and fuel respectively. The arithmetical sum of "a", "b", "c" and "d" shall be unity. "L" is the "Labour Index" and shall be
the actual Wage Rate index for all workers in the civil engineering industry
(weighted average for all areas) as published in the Statistical News Release
(P0142.2)
"P" is the "Plant Index" and shall be the "Civil Engineering Plant Index" as published in the Statistical News Release (PO 142.2) of the Central Statistical Service. "M" is the "Materials Index" and shall be
the "Price Index of Civil Engineering Materials",
"F" is the "Fuel Index" and shall be the
weighted average of the fuel indices for
The suffix "o" denotes the basic indices applicable to the base month, which shall be the month prior to the month in which the closing date for the tender falls. The suffix "t" denotes the current indices applicable to the month in which the last day of the period falls to which the relevant payment certificate relates.
If any index relevant to any particular certificate is not
known at the time when the certificate is prepared,
2. Assessment of amount subject to adjustment
For the purpose of calculating the adjustment to the value of the relevant certificates,
(ii) work done and the (iii) materials on Site before any adjustment made in terms of this Schedule. "S" is the aggregate of (i), (ii), (iii) and (iv), referred to below, and included in "T":
(ii) the value of any work done by Nominated Subcontractors; (iii) the value of any work done against Provisional Sums; (iv) the value of any extra or additional work; recorded at the time the work was ordered. "D" is the value of work included in "T" and done at new rates fixed in terms of Clauses 40(I) and 40(2), where those rates are not basedon labour, plant or materials costs in force at the time of tendering. Generallynew rates may be based on current costs and de-escalated to the base month of the indices, in which case work done at these rates shall not be included in thevalue of "D". "E" is the amount included in "T" and paid for any daywork executed at cost plus percentage allowances as set out in Clause 40(4). "G" is the amount included in "T" for materials classified and dealt with as "special materials" in terms of Clause 49(3). "Ap" is the summation of all "Ac" amounts determined in terms of Clause 2 of this Schedule for all certificates preceding in time the certificate under consideration. 3. Reduction of CPAF after Due Completion Date
Save only for additional work or variations ordered to be carried out after the Due Completion Date,
(1) The price of each "special material" specified in the Appendix shall be increased or decreased by the net amount
5. Assessment of indices if certificates are not issued monthly
If more than one month intervenes between the month applicable to any payment certificate and the month applicable
© Copyright 1990 by the South African Institution of Civil Engineering. ® All rights reserved |