COMMENCEMENT OF WORK

Back to Daily Tenders
Back to main Index Page

12  (1)    Commencement of Works
      (2)    Commencement Date

13  (1)    Access to and possession of Site
      (2)    Delays in giving possession
      (3)    Use of land

14  (1)    Basic survey references
      (2)    Contractors responsibility for setting out
      (3)    Errors in setting out

15  (1)    Order of Works

      (2)    Programme

      (3)    Supporting documents
      (4)    Adjustment of programme
      (5)    No relief of Contractors responsibilities

16  (1)    Custody of Drawings and Specifications
      (2)    Contractors copies
      (3)    Documents to be kept on Site
      (4)    Register of Drawings
      (5)    Drawings and Specifications
      (6)    Further Drawings, Specifications and instructions
      (7)    Contractor to give notice timeously
      (8)    Documents to be provided within reasonable times
      (9)    Contractor to give effect to Drawings, etc
      (10)  Engineers failure to comply timeously
      (11)  Engineer to approve Contractors designs and drawings

                                                                                        

Back to Top

12.(1) Commencement of Works

    The Contractor shall, save as may be otherwise provided in the Contract or be legally or physically impossible,
    commence executing the Works within the number of days stated in the Appendix calculated from
    the Commencement Date, excluding from the calculation any special non-working days, or by a later
    date specified in the written notice to the Contractor establishing the Commencement Date.

Back to Top

      (2) Commencement Date

    The Commencement Date shall not be later than 28 days after the date of delivery of the Letter of
    Acceptance unless otherwise agreed in terms of the Contract.

Back to Top

13.(1) Access to and possession of Site

    The Employer shall, subject to any requirements in the Contract as to the order in which the Works
    shall be executed,

(a) on the Commencement Date, give to the Contractor right of access to the Site, the location of
    which access shall be stated in the Tender Documents (including physical access to the extent
    stipulated in the Contract) and possession of so much of the Site as may be required to enable the
    Contractor to commence and proceed with the construction of the Works in accordance with
    the programme referred to in Clause 15, or otherwise in accordance with such reasonable proposals
    of the Contractor as he shall make by notice in writing to the Engineer and,

(b) from time to time as the Works proceed, give to the Contractor possession of such further portions
    of the Site as may be required to enable the Contractor to proceed with the construction of the
    Works with due despatch in accordance with the said programme or proposals as the case may be.

Back to Top

      (2) Delays in giving possession

    If the Contractor suffers any delay or additional Cost from failure of the Employer to give possession
    in accordance with the terms of this Clause, the Contractor shall be entitled to make a claim in accordance
    with Clause 5 1, for which purpose the time limit of 28 days provided in Clause 51(1)(a) shall commence to
    run only from the time when possession of the Site has actually been given and may be extended by the
    Engineer at his discretion.

Back to Top

      (3) Use of land

    The Contractor shall not use the Site or land connected with the Works, or cut down trees or vegetation,
    for any purpose whatsoever other than for the proper carrying out of the Works and shall locate any
    facilities that may be required for the Contract on the Site in such areas as the Engineer shall stipulate.

Back to Top

14.(1) Basic survey references

    The Engineer shall establish the basic reference pegs and benchmarks on the Site and give to the Contractor
    the particulars thereof in sufficient time to enable the Contractor to meet his approved programme.

Back to Top

  (2) Contractors responsibility for setting out

    After compliance by the Engineer with the provisions of Sub-Clause (1), the Contractor shall be responsible
    for the true and proper setting out of the Works and for the correctness of the position, levels, dimensions
    and alignment of all parts of the Works and for the provision of all necessary instruments, appliances and
    labour in connection therewith. The Contractor shall carefully protect and preserve a11 benchmarks,
    sight-rails, pegs and other things used in setting out the Works.
    The checking of any setting-out or of any line or level by the Engineer shall not relieve the Contractor
    of his responsibility for the correctness thereof.

Back to Top

  (3) Errors in setting out


    If at any time during the progress of the Works, any error shall appear or arise in the position, levels,
    dimensions or alignment of any part of the Works, the Contractor, on being required to do so by the Engineer,
    shall at his own expense rectify such error to the satisfaction of the Engineer, but if such error is based
    on incorrect data supplied in writing by the Engineer or if there is any delay in providing the particulars required
    in terms of Sub-C1ause (1), the Contractor shall, in respect of that delay and the Cost of such rectification,
    be entitled to make a claim in accordance with Clause 51.

Back to Top

15.(1) Order of Works


    The order in which the Works are to be carried out and the programme of construction shall be subject to
    the approval of the Engineer, which approval shall not be unreasonably withheld.

Back to Top

  (2) Programme

    The Contractor shall deliver to the Engineer within the time stated in the Appendix, calculated from the
    receipt by the Contractor of the Letter of Acceptance, a realistic programme showing the order of procedure
    and method which he proposes to use in carrying out the Works in order to meet the Due Completion Date.

Back to Top

  (3) Supporting documents

    When required by the Engineer, the Contractor shall, within a reasonable time, also deliver to the
    Engineer documents in support of the programme and particulars in writing of the Contractors resources
    planning, including

(a) the Contractors arrangements for and method of carrying out the Works, and

(b) the Constructional Plant which the Contractor intends to supply and use for the purpose of
    the Contract, and

(c) rates of progress for the various parts of the Works, and

(d) a detailed cash flow forecast.

Back to Top

  (4) Adjustment of programme

    The programme and the cash flow forecast shall be subject to review and, if so instructed by the Engineer,
    shall be adjusted by the Contractor on a regular monthly basis, or at such interval, as circumstances may require.

Back to Top

  (5) No relief of Contractors responsibilities

    The submission to and approval by the Engineer of such programme or its adjustment, or the delivery of
    any relevant particulars, shall not relieve the Contractor of any of his duties or responsibilities under
    the Contract.

Back to Top

16.(1) Custody of Drawings and Specifications

    The originals of all Drawings and Specifications prepared by or on behalf of the Engineer shall remain in
    his custody and references herein to delivery to the Contractor of Drawings or Specifications shall relate
    to true copies thereof.

Back to Top

  (2) Contractors copies


    The Contractor shall be entitled to receive free of charge, to the extent provided in the Contract, copies of
    each such Drawing and Specification and to receive, at the cost of reproduction, such additional copies as
    he shall reasonably require.

Back to Top

  (3) Documents to be kept on Site

    One copy of al documents constituting the Contract shall be kept on the Site and be available for perusal by
    the Engineer or any person authorised by him.

Back to Top

  (4) Register of Drawings

    The Contractor shall, in accordance with the Engineers instructions, maintain a register on the Site
    of all Drawings and revisions thereof in the chronological order in which they are delivered to him.

Back to Top

  (5) Drawings and Specifications

    On the Commencement Date the Engineer shall deliver to the Contractor copies of the Drawings,
    Specifications and other relevant documents required for the commencement of the Works.

Back to Top

  (6) Further Drawings, Specifications and instructions

    The Engineer shall deliver to the Contractor from time to time, during the progress of the Works, such modified
    or further Drawings and Specifications or instructions as shall, in the Engineers opinion, be necessary for
    the proper and adequate construction, completion and defects correction of the Works.

Back to Top

  (7) Contractor to give notice timeously

    The Contractor shall give adequate notice in writing to the Engineer of any additional Drawing or
    Specification which the Contractor may require for the execution of the Works and the Engineer shall deliver
    such Drawing or Specification to the Contractor.

Back to Top

  (8) Documents to be provided within reasonable times

    The Drawings, Specifications and instructions aforesaid shall be delivered within times which are
    reasonable having regard to all the circumstances, and taking account of the provisions of any
    programme submitted to the Engineer in terms of Clause 15 and approved by him.

Back to Top

  (9) Contractor to give effect to Drawings, etc.


    The Contractor shall give effect to and be bound by any Drawing, Specification or instruction given in terms
    of this Clause and, if the same shall require any variation of, addition to, or omission from the Works,
    the same shall be deemed to have been issued in terms of Clause 39.

Back to Top

  (10) Engineers failure to comply timeously

    If by reason of a failure by the Engineer, after his receipt of written notice from the Contractor in terms of
    Sub-Clause (7), to comply timeously with the provisions of Sub-Clause (8), the Contractor shall suffer any
    delay or incur any Cost, he shall be entitled to make a claim in accordance with Clause 51, for which purpose
    the time limit of 28 days in Clause 51(1)(a) may be extended by the Engineer at his discretion.

Back to Top

  (11) Engineer to approve Contractors designs and drawings

    If the Contract expressly provides for the preparation by the Contractor of designs and details of any work to
    be supplied, he shall submit for approval by the Engineer, in triplicate, a drawing giving full details, dimensions
    and particulars together with all relevant information and erecting or operating instructions (if any) and
    shall obtain the Engineers written approval, which shall be given within a reasonable time,
    before commencing the work.

    When any such Drawing has been approved by the Engineer, it shall not be departed from in any way except
    with the written consent of the Engineer.