LiveZilla Live Help
www.dailytenders.co.za
VARIATIONS

Back to Daily Tenders
Back to main Index Page

39. (1)   Variations
      (2)   Orders for variations to be in writing
      (3)   Changes in scheduled quantities

40. (1)   Valuation of variations
      (2)   Changing of unreasonable or inapplicable rates 
      (3)   Notices of change to be given in writing
      (4)   Daywork

                                                                                                     

Back to Top

39.(1) Variations

      If, at any time before the issue of the Certificate of Completion, the Engineer shall require any variation of
      the form, quality or quantity of the Works or any part thereof that may in his opinion be necessary or
      for any reason appropriate, he shall have power to order the Contractor to do any of the following:

(a) increase or decrease the quantity of any work included in the Contract,

(b) omit any such work,

(c) change the character or quality of any such work,

(d) change the levels, lines, position and dimensions of any part of the Works,

(e) execute additional work of any kind necessary for the completion of the Works, and

(f) change the specified or approved sequence or method of construction.

      No such variation shall in any way vitiate or invalidate the Contract, but the value (if any) of all such variations
      shall be taken into account in ascertaining the amount of the Contract Price.

Back to Top

    (2) Orders for variations to be in writing


      No such variation shall be made by the Contractor without an order in writing 
      (herein referred to as a "Variation Order") by the Engineer;

      Provided that,

(a) if for any reason the Engineer shall consider it desirable to give such order orally, the Contractor
      shall comply with such order and any confirmation in writing of such oral order given by the
      Engineer, whether before or after the carrying out of the order, shall be deemed to be a Variation
      Order within the meaning of this Clause, or

(b) if the Contractor, as soon as possible, but within 14 days after receiving such oral order or a written
      order which he contends to be a Variation Order, confirms it in writing to the Engineer as being a
      Variation Order and such confirmation is not contradicted in writing by the Engineer to the
      Contractor within 14 days of receipt thereof, it shall be deemed to be a Variation Order within the
      meaning of this Clause.

Back to Top

    (3) Changes in scheduled quantities

      No increase or decrease in the quantity of any work scheduled, where such increase or decrease is not
      the result of a Variation Order given under this Clause but is the result of the quantities exceeding or being
      less than those stated in the Schedule of Quantities, shall be deemed to be a variation to which this Clause
      applies and no order in writing shall be required therefore.

40.(1) Valuation of variations

Back to Top

      The value of all variations ordered by the Engineer in accordance with Clause 39 shall be calculated by the
      Engineer, after consultation with the Contractor, in accordance with the following principles:

(a) where work is of a similar character and executed under similar conditions to work priced in the
      Schedule of Quantities, it shall be valued at such rates and prices
      (including Preliminary and General allowances) contained therein as may be applicable; or

(b) where work is not of a similar character or is not executed under similar conditions, the rates and
      prices in the Schedule of Quantities shall be used as the basis for valuation as far as may be
      reasonable; or

(c) where work cannot reasonably be valued in accordance with paragraphs (a) or (b), a fair value shall
      be determined; or

(d) in respect of additional or substituted work, if none of the above principles are applicable,
      the work shall be executed on a daywork basis in terms of Sub-Clause (4);

      Provided that, failing agreement with the Contractor, the Engineer shall determine the rate or
      price in accordance with the aforegoing principles, notify the Contractor in writing accordingly and apply
      the said determination in his certification of amounts payable to the Contractor, without prejudice to the
      Contractors right to raise a disagreement in terms of Clause 60.

(2) Changing of unreasonable or inapplicable rates

Back to Top

      Notwithstanding the provisions of Sub-Clause (1), if the nature or amount of any variation or
      increase or decrease in quantity, whether ordered under Clause 39 or being the result of the
      quantities exceeding or being less than those stated in the Schedule of Quantities, relative to the nature
      or amount of the whole or the relevant part of the work specified in the Contract, shall be such that it results
      in a change in method or scale of operation, process of construction or source of supply which will render any
      rate or price (including Preliminary and General allowances) contained in the Contract for any item of work
      unreasonable or inapplicable, either the Engineer or the Contractor shall be entitled, in compliance with
      Sub-Clause (3) to require that a rate or price be fixed which, in the circumstances, is fair and reasonable.

(3) Notice of change to be given in writing

Back to Top

      No change in terms of this Clause shall be made to the Contract Price or to any rate or price unless,
      as soon as is practicable, and in the case of extra or additional work before the commencement of such work,
      notice shall have been given in writing

(a) by the Contractor to the Engineer of his intention to claim extra payment in terms of Sub-Clause (1)
      or a varied rate or price in terms of Sub-Clause (2), or

(b) by the Engineer to the Contractor of his intention to vary a rate or price in terms of
      Sub-C1ause (2).

(4) Daywork

Back to Top

(a) If work is to be executed on a daywork basis in terms of Sub-Clause (1)(d), the Contractor shall be
      paid for such work under the provisions set out in the Daywork Schedule included in the Tender
      and at the rates and prices stated therein.

(b) In the absence of a Daywork Schedule, the Contractor shall be paid the aggregate of

(i) the gross remuneration of the workmen and of any foremen for the time they are actually
      engaged on the work concerned,

(ii) the net cost of the materials actually used,

(iii) the percentage allowances stated in the Appendix, which allowances shall be held to
      cover all charges for the Contractors and subcontractors profits, timekeeping, clerical
      work, insurance, establishment, superintendence and the use of hand tools, and

(iv) an amount in respect of Constructional Plant calculated as provided for in
      paragraph (c).

(c) The use of Constructional Plant shall be charged on a time basis at the rates stated in the Tender,
      failing which at rates to be agreed between the Contractor and the Engineer or, failing agreement,
      to be determined by the Engineer on the basis of ruling plant hire rates.

(d) If required by the Engineer, the Contractor shall, before ordering material, submit to the Engineer
      quotations for the same for his approval, which approval shall not be unreasonably withheld,
      and shall produce to him such receipts or other vouchers as may be necessary to prove the
      amounts paid.

(e) The Contractor shall, during the continuance of all work executed on a daywork basis, deliver each
      day to the Engineer or the Engineers Representative in triplicate a list of the exact occupation and
      time of all workmen and foremen employed on such work and a statement showing the description
      and quantity of all materials and Constructional Plant used therefore (other than tools the cost of
      which is covered by the percentage addition in accordance with the Daywork Schedule in terms
      of which payment for daywork is made). The Engineer or the Engineers Representative shall,
      on the copies of each list and statement, record in writing, signed by him, the extent to which he
      agrees with the accuracy thereof and return those copies to the Contractor.

(f) For the purpose of each monthly certificate referred to in Clause 52(1), the Contractor shall deliver
      to the Engineer a priced statement of the labour, materials and Constructional Plant used
      (except as provided in paragraph (e)) and the Contractor shall not be entitled to any payment for
      the daywork concerned unless and until such statement has been properly rendered and supported
      by one copy of each of the signed lists and statements referred to in paragraph (e).

Back to Top
Back to main Index Page

© Copyright 1990 by the South African Institution of Civil Engineering. ® All rights reserved